The project is executed in association “Čistý Černý Důl”, BAK stavební společnost, a.s. makes a part of. The scope of work is construction of new wastewater treatment plant 3500EO with outflow building, wastewater treatment plant outlet and all respective connections. Project consists of new gravitational sewage in total length of 5 112 m out of which gravitational conduit DN 300 in total length of 3 296 m with diameter DN 250 in total length of 1 816 m and 249 m of pressure conduit.
What did we build?
Sewage and wastewater treatment plant in Černý Důl
Investor:
Černý Důl
Location:
Realization:
09/2017 - 07/2019